128 Notice of Suspension arising from the late payment.doc
- 【下载声明】
1. 本站全部试题类文档,若标题没写含答案,则无答案;标题注明含答案的文档,主观题也可能无答案。请谨慎下单,一旦售出,不予退换。
2. 本站全部PPT文档均不含视频和音频,PPT中出现的音频或视频标识(或文字)仅表示流程,实际无音频或视频文件。请谨慎下单,一旦售出,不予退换。
3. 本页资料《128 Notice of Suspension arising from the late payment.doc》由用户(无敌的果实)主动上传,其收益全归该用户。163文库仅提供信息存储空间,仅对该用户上传内容的表现方式做保护处理,对上传内容本身不做任何修改或编辑。 若此文所含内容侵犯了您的版权或隐私,请立即通知163文库(点击联系客服),我们立即给予删除!
4. 请根据预览情况,自愿下载本文。本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
5. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007及以上版本和PDF阅读器,压缩文件请下载最新的WinRAR软件解压。
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 128 Notice of Suspension arising from the late payment
- 资源描述:
-
1、DIAR DUSHANBE PROJECT PHASE 1Ref No: SHY/DDP/PE1/12/128 Date: 11th November, 2012To: Mr. Sadettin Otluoglu Resident EngineerDAR Muhendislik Musavirlik A.S.AINI Street 24a “Markazai Tijori” CJSC “S.A.S”, 3rd FloorDushanbe, Tajikistan 734012Tel: +992(44)601 92 88RE: Contract ID: 55002348 Construction
2、of Diar Dushanbe Project - Phase1Subject: Notice of Suspension Our Ref.: SHY/DDP/PE1/12/101 Your Ref.: QDDP-IMS-SNH-121108-849_Dear Sir,Your letter has been duly reviewed and we hereby respond as follows:1. We agree with your statement “the submission of the Performance Security is a pre-requisite f
3、or the Advance Payment”. As you know that it took 2months to finalize the Performance Security since from the Kick-off meeting due to many reasons, which consequentially resulted into the unreasonable delay of effect of the Advance Payment. The letter we submitted should be served you as our kind re
4、minders to earlier effect the Payment so that we can mobilize various resources for the subject Project without any further delay. At the juncture, no final agreement seems to be likely reached due to the extra terms of assignment of Guarantee initiated by the Employer. 2. Although we have got the B
5、ank Loan for execution of the Work, the cash flow was being alarmed and no options but to reduce the rate of Work till 9th October 2012. You may understand that the financing charge is to be borne by the Contractors shoulder, which is not acceptable to us because the Employer shall make an advance p